Download (right click)
this sample file as:
PDF
Word
Sample
of Geothermal Loopfield Specifications
Closed Circuit Vertical Heat Exchanger (VHE)
Description of Work
A. This design
has been prepared in accordance with the materials
standards and accepted installation practices of the
(IGSHPA). The loopfield contractor shall comply
with these standards and practices as well as all State
and local regulations pertaining to the installation.
B. The loopfield
contractor is responsible for all aspects involved with
the complete geothermal loopfield installation. All
materials, drilling, excavation, hauling of backfill,
pumping, soil compaction and labor required shall be
included in the bid price.
C. The loopfield
contractor shall take note: there is no guarantee to
the loopfield contractor that the location of any
existing utilities are exactly as
indicated on the plans.
Some areas may require hand digging to locate that
utility. The loopfield contractor must include in the
bid price, the repair of any domestic water, electrical,
communication or any service line that may be damaged
during the construction of this project. Any offsets
required to route over or
under existing lines
shall also be included in the bid price of the project.
Qualifications
A. The
loopfield contractor must have on this project a
certified IGSHPA installer. The loopfield
contractor performing this work must have a minimum of
two years experience in performing underground closed
circuit VHE work of this project's size or larger.
B. VHE fabricators
must be heat fusion certified by an authorized high
density polyethylene (HDPE) pipe manufacturer's
representative of the brand of pipe used. Certification
must include: successful completion of a written heat
fusion exam as well as demonstrating proper heat fusion
techniques under the direct supervision of the
authorized HDPE pipe manufacturer's representative.
Products
A.
Pipe
The pipe shall be PE3408 HDPE with a minimum cell
classification of 45434C per ASTM D3035-93 and a SDR11
(160 psi) rating for u-bends and header pipe 2 inches or
smaller and a minimum of DR15.5 (110 psi) for header
pipe greater than 2 inch in diameter. This pipe will
carry a warranty of no less than 25 years.
Each pipe shall be
permanently indent marked with the manufacturer's name,
nominal size, pressure rating, relevant ASTM standards,
cell classification number and date of manufacture.
All piping used for
VHE will have factory hot-stamped lengths impressed on
the side of the piping indicating the length of the VHE
at that point. The length stamp shall read zero on one
end and the actual VHE total length on the other end.
The VHE will have a
factory fused u-bend with pipe lengths long enough to
reach grade from the bottom of the bore so no field
fusions are required below the header pit.
B.
Vaults/Manifolds
The vault structure should be a composite structure of
steel and concrete. The inner shell consists of a
heavy-duty steel frame and base with steel interior
walls, ceiling and floor that are specially treated with
a rubberized rust resistant coating. The outer shell of
the wall and ceiling consists of 8" thick reinforced
poured concrete.
The vault is shipped
from the manufacturer preformed for concrete pour with
all reinforcement rods, manifolds, and piping secured in
place. The vault is set on an 18" level base of
compacted gravel. Concrete, supplied by the contractor,
is then poured into the vault form and screeded off the
top of the form. Once the concrete cures, the outer
form walls are removed and the vault is ready to fuse on
the circuit and manifold piping.
HDPE pipe, joined
together with heat fusion, should be used for all of the
vault's circuit and main header piping. This HDPE pipe
is tough, non-corrosive, and leak proof. All of the
vault's circuits include valves and pressure/temperature
ports for complete isolation, pressure testing and flow
balancing. Acceptable manifolds are manufactured by
GHP Systems, Inc.
C.
Fittings
Pipe fittings shall meet the requirements of ASTM D2683
(for socket fusion fittings) or ASTM D3261 (for
butt/saddle fusion fittings). Each fitting shall be
identified with the manufacturer's name, nominal size,
pressure rating, relevant ASTM standards and date of
manufacturer.
D.
U-bend Pipe Separators
The u-bend pipe separators used to position the u-bend
pipes against the borehole wall directly across from one
another -- shall be the GeoClip brand
manufactured by GBT, Inc. These separators will
be positioned every ten feet on the u-bend pipe.
E.
Bentonite Grout
The thermally enhanced bentonite grout used to seal the
VHE shall have a minimum thermal conductivity of 0.57
Btu/hr-ft°F and a minimum of 43% solids. This grout
will also have a permeability rate of less than 1X10-7cm/sec.
F.
Locating Tape
Locating tape must be foil backed, two inches wide or
greater, with a continuous message printed every 36
inches or less reading: "CAUTION GEOTHERMAL PIPELINE
BURIED BELOW". The tape shall be highly
resistant to alkalis,
acids, and other destructive agents found in the ground.
G. Field Location
The four outside grid bores should be surveyed after
drilling is complete, but before horizontal trenching is
done.
Execution
A.
Drilling
The vertical boreholes will be drilled to a depth that
allows complete insertion of the VHE to its specified
depth. The maximum borehole diameter will be six
inches. If a larger diameter is required, it must be
approved by the design engineer.
B. U-bend Pipe
Assembly
The u-bend pipe shall be filled with water and pressured
to 100 psi to check for leaks before insertion. If
necessary, an iron (sinker) bar can be attached at the
base of each u-bend to overcome bouncy. This iron bar
will have all sharp edges adequately taped to avoid
scarring and/or cutting of the polyethylene pipe. No
driving rod that is pulled out after u-bend insertion
will be allowed. U-bend pipe separators (GeoClips)
will be attached at ten feet intervals to the u-bend
along with the grouting tremie as per manufacturer's
recommendations. The entire u-bend pipe assembly is
inserted to the specified depth in the borehole.
C.
Grouting Procedure
The VHE is to be grouted from the bottom up, in a
continuous fashion, using a one inch HDPE tremie pipe.
The tremie pipe will be pulled out during the grouting
procedure maintaining the pipe's end just below grout
level within the borehole. All State regulations will
be met for borehole grouting of the VHE.
D.
Heat Fusion Pipe Joining
All underground pipe joining will be heat fused by
socket, butt or saddle (sidewall) fusion in accordance
to ASTM D2610, ASTM D2683 and the manufacturer's heat
fusion specifications. The operator shall be heat
fusion certified and experienced in executing quality
fusion joints.
E. Excavation and
Backfilling for Piping
The loopfield contractor shall do all excavating,
backfilling, shoring, bailing and pumping for the
installation of his work and perform necessary grading
to prevent surface water from flowing into trenches or
other excavations. Sewer lines shall not be used for
draining trenches. All pipe and conduit ends shall be
kept sealed and lines left clean and unobstructed during
construction. Only material suitable for backfilling
shall be piled a sufficient distance from banks of
trenches to avoid overloading. Unsuitable backfill
material shall be removed as directed by the design
engineer.
Sheathing and shoring
shall be done as necessary for protection of work and
personnel safety. Unless otherwise indicated,
excavation shall be open cut except for short sections.
The loopfield contractor
shall install geothermal locating tape 18 inches above
all horizontal/header piping.
Prior to drilling or
trenching, the loopfield contractor shall be responsible
for reviewing with the general contractor the location
of underground utilities. Existing utility lines
uncovered during excavation shall be protected from
damage during excavation and backfilling.
F.
Pipe Installation
The u-bend pipe ends will be sealed with fusion caps or
tape prior to insertion into the borehole. Reasonable
care shall be taken to ensure that the geothermal
loopfield pipe is not crushed, kinked, or cut. Should
any pipe be damaged, the damaged section shall be cut
out and the pipe reconnected by heat fusion.
The VHEs must be
connected as indicated on the plans. The header design
accounts for balanced flow as well as flushing and
purging flow rates. No variations can be made in the
circuit hookup or the pipe sizes that are indicated
without approval from the design engineer. The minimum
bend radius for each pipe size shall be 25 times the
nominal pipe diameter or the pipe manufacturer's
recommendations, whichever is greater. The depth of all
headers and supply and return piping is indicated on the
plans and must be maintained.
Circuits will be
pressure tested before any backfilling of the header
trenches is executed. The individual circuits will be
pressure tested with water at 60 psi, however, not to
exceed DR 11 pipe working pressure at bottom of the
u-bend pipe.
Testing and Cleaning
A.
Cleaning
During installation, all debris, and small animals shall
be kept out of the pipe. Ends of the HDPE pipe shall be
sealed until the pipe is joined to the circuits.
B.
Flushing and Purging
Each supply and return circuit shall be flushed and
purged with a water velocity of two feet per second.
The lines shall be left filled with clean water and then
pressure tested. If connection to the manifold is not
immediate, piping must be capped. The loopfield
contractor must coordinate with the mechanical
contractor on propylene glycol antifreeze installation.
The mechanical contractor is responsible for the
propylene glycol antifreeze. See mechanical
specifications for antifreeze.
Shop Drawings and
Inspection of Geothermal Loopfield
A. Before
geothermal loopfield construction begins, the loopfield
contractor must submit shop drawings to the design
engineer. The shop drawings shall include all
applicable manufacturer's specifications, warranties,
and material safety data sheets for all materials used
in the geothermal installation. No substitutions will
be allowed without authorization from the design
engineer. |